Optimizing Air Quality in Schools

North Bay, Ontario

completeVentilationCVRIS
Federal contribution
$691,982
Federal share80%

of $865.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 14, 2021
202220232024
Built

Approved 8 weeks before the announcement.

Program
COVID-19 Resilience Stream
Construction start
Oct 20, 2021(actual)
Construction end
Dec 31, 2023(actual)

Against the original forecast

  • Construction start8 months lateforecast Feb 18, 2021

Also in North Bay

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 58719 in the federal list. How to read these figures.