Modernization of the administrative spaces on the 3rd floor - avenue Decelles

Montréal, Quebec

completeHealthcare InfrastructureCVRIS
Federal contribution
$4.9M
$4,854,248
Federal share78%

of $6.2M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 7, 2021
2022
Built

Approved 5 months before the announcement.

Program
COVID-19 Resilience Stream
Construction start
Aug 24, 2021(actual)
Construction end
Aug 26, 2022(actual)

Against the original forecast

  • Construction start2 months lateforecast Jun 14, 2021
  • Construction end5 weeks lateforecast Jul 23, 2022

Also in Montréal

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 58774 in the federal list. How to read these figures.