Modernization of the administrative spaces on the 3rd floor - avenue Decelles
Federal contribution
$4.9M
$4,854,248
Federal share78%
of $6.2M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 7, 2021
2022
Built
Approved 5 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Centre hospitalier universitaire Sainte-Justine
- Construction start
- Aug 24, 2021(actual)
- Construction end
- Aug 26, 2022(actual)
Against the original forecast
- Construction start2 months lateforecast Jun 14, 2021
- Construction end5 weeks lateforecast Jul 23, 2022
Also in Montréal
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 58774 in the federal list. How to read these figures.