Repair of the main entrance
Salaberry-de-Valleyfield, Quebec
Federal contribution
$429,600
Federal share80%
of $537.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 7, 2021
2022
Built
Approved 5 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Centre intégré de santé et de services sociaux de la Montérégie-Ouest
- Construction start
- May 19, 2021(actual)
- Construction end
- Mar 24, 2022(actual)
Against the original forecast
- Construction start3 months lateforecast Mar 1, 2021
- Construction end3 months lateforecast Dec 15, 2021