Block B cooler replacement
Salaberry-de-Valleyfield, Quebec
Federal contribution
$693,302
Federal share79%
of $875.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 7, 2021
2022
Built
Approved 5 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Centre intégré de santé et de services sociaux de la Montérégie-Ouest
- Construction start
- Mar 8, 2021(actual)
- Construction end
- Jan 28, 2022(actual)
Against the original forecast
- Construction end2 months lateforecast Nov 15, 2021
Also in Salaberry-de-Valleyfield
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 58779 in the federal list. How to read these figures.