Back to projects

Block B cooler replacement

Salaberry-de-Valleyfield, Quebec

completeHealthcare InfrastructureCVRIS
Federal contribution
$693,302
Federal share79%

of $875.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 7, 2021
2022
Built

Approved 5 months before the announcement.

Program
COVID-19 Resilience Stream
Construction start
Mar 8, 2021(actual)
Construction end
Jan 28, 2022(actual)

Against the original forecast

  • Construction end2 months lateforecast Nov 15, 2021

Also in Salaberry-de-Valleyfield

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 58779 in the federal list. How to read these figures.