Back to projects

Installation of a magnetic centrifugal chiller with a capacity of 194 tonnes at the 1001 St-Denis

Montréal, Quebec

completeVentilationCVRIS
Federal contribution
$795,000
Federal share80%

of $993.8K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 7, 2021
202220232024
Built

Approved 5 months before the announcement.

Program
COVID-19 Resilience Stream
Construction start
Sep 21, 2021(actual)
Construction end
Dec 4, 2023(actual)

Against the original forecast

  • Construction start7 weeks lateforecast Aug 5, 2021
  • Construction end6 months lateforecast May 31, 2023

Also in Montréal

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 58781 in the federal list. How to read these figures.