Replacement of generators (phase 2)
Federal contribution
$3.0M
$3,000,000
Federal share80%
of $3.8M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 7, 2021
202220232024
Built
Approved 5 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Centre intégré de santé et de services sociaux de l'Outaouais
- Construction start
- Apr 26, 2021(actual)
- Construction end
- Nov 23, 2023(actual)
Against the original forecast
- Construction start4 weeks lateforecast Apr 1, 2021
- Construction end17 months lateforecast Jun 30, 2022
Also in Gatineau