Back to projects

Replace the 3 curtain walls (phase 3)

Gatineau, Quebec

completeHealthcare InfrastructureCVRIS
Federal contribution
$1.0M
$1,009,569
Federal share80%

of $1.3M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 7, 2021
20222023
Built

Approved 5 months before the announcement.

Program
COVID-19 Resilience Stream
Construction start
Jun 28, 2021(actual)
Construction end
May 15, 2023(actual)

Against the original forecast

  • Construction start4 weeks lateforecast Jun 1, 2021
  • Construction end17 months lateforecast Dec 17, 2021

Also in Gatineau

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 58784 in the federal list. How to read these figures.