Replace the 3 curtain walls (phase 3)
Federal contribution
$1.0M
$1,009,569
Federal share80%
of $1.3M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 7, 2021
20222023
Built
Approved 5 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Centre intégré de santé et de services sociaux de l'Outaouais
- Construction start
- Jun 28, 2021(actual)
- Construction end
- May 15, 2023(actual)
Against the original forecast
- Construction start4 weeks lateforecast Jun 1, 2021
- Construction end17 months lateforecast Dec 17, 2021
Also in Gatineau