Back to projects

Renovation Providing Safe Reopening for Community

North Grenville, Ontario

completeRecreationCVRIS
Federal contribution
$80,000
Federal share80%

of $100.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 15, 2021
2022
Built

Approved 3 months before the announcement.

Program
COVID-19 Resilience Stream
Construction start
Aug 19, 2021(actual)
Construction end
Jun 21, 2022(actual)

Also in North Grenville

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 58810 in the federal list. How to read these figures.