New Construction of Polyvinyl Chloride (PVC) Gravity Sanitary Main on County Road 44
Federal contribution
$189,015
Federal share44%
of $431.4K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 23, 2017
2018
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Municipality of North Grenville
- Construction start
- May 15, 2017(actual)
- Construction end
- Sep 4, 2018(actual)
Against the original forecast
- Construction start2 weeks lateforecast May 1, 2017
Also in North Grenville
- Expansion and upgrade of County Road 43 and rehabilitation of bridge across Kemptville Creek$5.0M
- HVAC; Other Improvements to Air Quality and Duct Sealing; Water Bottle Filling Station; Fence$3.5M
- County Road 44 Multi-Use Pathway Extension$942.0K
- Rehabilitation of Concession Road Watermains$390.9K
- Renovation Providing Safe Reopening for Community$80.0K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49660 in the federal list. How to read these figures.