New Construction of Polyvinyl Chloride (PVC) Gravity Sanitary Main on County Road 44

North Grenville, Ontario

completeWastewaterCWWF
Federal contribution
$189,015
Federal share44%

of $431.4K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 23, 2017
2018
Built
Program
Clean Water and Wastewater Fund
Construction start
May 15, 2017(actual)
Construction end
Sep 4, 2018(actual)

Against the original forecast

  • Construction start2 weeks lateforecast May 1, 2017

Also in North Grenville

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49660 in the federal list. How to read these figures.