Increase in the capacity of the electrical panel at the long term care facility - Centre d'hébergement (CH) de Lachine
Federal contribution
$960,000
Federal share80%
of $1.2M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 7, 2021
2021202220232024
Built
Approved 5 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Centre intégré universitaire de santé et de services sociaux de l'Ouest-de-l'Île-de-Montréal
- Construction start
- Mar 20, 2023(actual)
- Construction end
- May 29, 2024(actual)
Against the original forecast
- Construction end5 weeks earlyforecast Jun 30, 2024
Also in Montréal-Ouest
- Reconstruction of the sports and recreation center$6.3M
- Replacement of MCCs (Main Electrical Distribution) at Lakeshore General Hospital (LGH) - Phase 5$2.1M
- Repair and upgrades to the University Family Medicine Group (GMF-U) department as well as to the H Norma and Robert Hayes buildings of the St. Mary's Hospital Center (SMHC)$1.2M
- Renewal of water pipes$869.1K
- Refurbishment of the envelope of building 01400-01 at Hôpital Sainte-Anne$800.0K