Increase in the capacity of the electrical panel at the long term care facility - Centre d'hébergement (CH) de Lachine

Montréal-Ouest, Quebec

completeVentilationCVRIS
Federal contribution
$960,000
Federal share80%

of $1.2M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 7, 2021
2021202220232024
Built

Approved 5 months before the announcement.

Program
COVID-19 Resilience Stream
Construction start
Mar 20, 2023(actual)
Construction end
May 29, 2024(actual)

Against the original forecast

  • Construction end5 weeks earlyforecast Jun 30, 2024

Also in Montréal-Ouest

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 58820 in the federal list. How to read these figures.