Renewal of water pipes

Montréal-Ouest, Quebec

completeDrinking WaterCWWF
Federal contribution
$869,096
Federal share35%

of $2.5M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 18, 2017
Built

Approved 3 months before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
City of Montréal West
Construction start
May 17, 2017(actual)
Construction end
Oct 31, 2017(actual)

Against the original forecast

  • Construction start6 weeks earlyforecast Jun 28, 2017
  • Construction end5 months earlyforecast Mar 31, 2018