Air conditionning in clinical (C71, C61, C51) and store (M06) sectors at the Institut universitaire de cardiologie et de pneumologie de Québec Université Laval (IUCPQ-UL)
Federal contribution
$800,000
Federal share80%
of $1.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 7, 2021
2022
Built
Approved 5 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Institut universitaire de cardiologie et de pneumologie de Québec - Université Laval
- Construction start
- Aug 17, 2021(actual)
- Construction end
- May 14, 2022(actual)
Against the original forecast
- Construction end5 months lateforecast Nov 30, 2021