Repair of park D and the water inlet of pavilion Y - Lot 3 at the Institut universitaire de cardiologie et de pneumologie de Québec – Université Laval (IUCPQ-UL).

Québec, Quebec

completeHealthcare InfrastructureCVRIS
Federal contribution
$326,406
Federal share67%

of $490.7K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 7, 2021
2022
Built

Approved 5 months before the announcement.

Program
COVID-19 Resilience Stream
Construction start
Aug 10, 2021(actual)
Construction end
Jan 14, 2022(actual)

Against the original forecast

  • Construction start6 weeks lateforecast Jul 1, 2021
  • Construction end2 months lateforecast Nov 1, 2021

Also in Québec