Back to projects

Repair of Exterior Entrances

Alma, Quebec

completeEducation, Training and ChildcareCVRIS
Federal contribution
$286,291
Federal share72%

of $400.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 8, 2021
20222023
Built

Approved 4 months before the announcement.

Program
COVID-19 Resilience Stream
Ultimate recipient
Collège d'Alma
Construction start
Aug 2, 2021(actual)
Construction end
Sep 30, 2023(actual)

Against the original forecast

  • Construction end4 weeks lateforecast Aug 30, 2023

Also in Alma

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 58862 in the federal list. How to read these figures.