Back to projects

Wing B Enhancement

Québec, Quebec

completeVentilationCVRIS
Federal contribution
$2.1M
$2,145,600
Federal share35%

of $6.1M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 8, 2021
2022
Built

Approved 4 months before the announcement.

Program
COVID-19 Resilience Stream
Ultimate recipient
Cégep de Sainte-Foy
Construction start
Mar 15, 2021(actual)
Construction end
Jan 17, 2022(actual)