Rehabilitation of the curtain wall at 5252 de Maisonneuve Ouest

Montréal, Quebec

completeHealthcare InfrastructureCVRIS
Federal contribution
$1.0M
$1,011,720
Federal share80%

of $1.3M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 7, 2021
202220232024
Built

Approved 5 months before the announcement.

Program
COVID-19 Resilience Stream
Construction start
Apr 12, 2021(actual)
Construction end
Dec 5, 2023(actual)

Against the original forecast

  • Construction end4 weeks earlyforecast Dec 31, 2023