Replacement of the waterproofing system aimed at solving the problem of occasional water infiltration from the kitchen on the 4th of Pavilion C and D to the 3rd at the Montreal General Hospital
Federal contribution
$1.1M
$1,102,080
Federal share80%
of $1.4M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 7, 2021
202220232024
Built
Approved 4 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Centre universitaire de santé McGill
- Construction start
- Apr 12, 2021(actual)
- Construction end
- May 30, 2024(actual)