Back to projects

COVID 19 Facility and AV Upgrades

Peterborough, Ontario

completeAdministration, Emergency and Public WorksCVRIS
Federal contribution
$83,494
Federal share80%

of $104.4K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 15, 2021
2022
Built

Approved 4 months before the announcement.

Program
COVID-19 Resilience Stream
Ultimate recipient
County of Peterborough
Construction start
Aug 13, 2021(actual)
Construction end
Nov 8, 2022(actual)

Also in Peterborough

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 58931 in the federal list. How to read these figures.