New Tecumseth Recreation Centre Roof Replacement
Federal contribution
$393,116
Federal share80%
of $491.4K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 29, 2021
Built
Approved 4 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Town of New Tecumseth
- Construction start
- Jun 22, 2021(actual)
- Construction end
- Dec 6, 2021(actual)
Also in New Tecumseth
- Improvements to Riverdale Park in Alliston$529.3K
- New Construction, Standby Emergency Power for Wells #1, #4, #8, and Hillcrest Pump Station$412.5K
- Replacement of Single Train Membrane at Raymond A. Barker Water Treatment Plant located at 2 Raglan Street, Collingwood$236.8K
- Upgrades to Well #1 including replacement of pump with a higher rated pump, and the increase size of the Chlorine Contact Chamber, at 46 Fletcher Lane, Alliston, Ontario$168.5K
- Construction of a Multi-Use Accessible Pedestrian Trail along Boyne River in community of Alliston$160.0K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 58951 in the federal list. How to read these figures.