Back to projects

New Construction, Standby Emergency Power for Wells #1, #4, #8, and Hillcrest Pump Station

New Tecumseth, Ontario

completeDrinking WaterCWWF
Federal contribution
$412,500
Federal share47%

of $875.0K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 16, 2017
ApprovedMar 27, 2018
201820192020
Built

Approved 9 months after the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Town of New Tecumseth
Construction start
Jun 11, 2017(actual)
Construction end
Oct 6, 2020(actual)

Against the original forecast

  • Construction start6 weeks lateforecast May 1, 2017
  • Construction end13 months lateforecast Aug 30, 2019

Also in New Tecumseth

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 50186 in the federal list. How to read these figures.