Upgrading of sanitary blocks
Federal contribution
$359,100
Federal share75%
of $481.8K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 8, 2021
2022
Built
Approved 4 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Cégep Gérald-Godin
- Construction start
- Jun 2, 2021(actual)
- Construction end
- Feb 14, 2022(actual)
Against the original forecast
- Construction end4 weeks lateforecast Jan 17, 2022
Also in Montréal
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 58970 in the federal list. How to read these figures.