Back to projects

Sports Locker Rooms Retrofit

Montréal, Quebec

completeEducation, Training and ChildcareCVRIS
Federal contribution
$984,400
Federal share64%

of $1.5M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 8, 2021
Built

Approved 4 months before the announcement.

Program
COVID-19 Resilience Stream
Ultimate recipient
Collège de Rosemont
Construction start
Mar 15, 2021(actual)
Construction end
Dec 3, 2021(actual)

Also in Montréal