Municipal Fire Hall Rehabilitation/Upgrading
Federal contribution
$80,000
Federal share80%
of $100.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 15, 2021
20222023
Built
Approved 4 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Township of Papineau-Cameron
- Construction start
- May 10, 2022(actual)
- Construction end
- Jun 1, 2023(actual)
Against the original forecast
- Construction start12 months lateforecast May 15, 2021
- Construction end20 months lateforecast Oct 15, 2021
Also in Papineau-Cameron