Multiple Stormwater control systems Rehabilitation of structual upgrades/restoration, and replacement of multiple stormwater culverts
Federal contribution
$50,000
Federal share10%
of $520.8K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 24, 2017
2017
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Township of Papineau-Cameron
- Construction start
- Jun 1, 2016(actual)
- Construction end
- Nov 8, 2017(actual)
Against the original forecast
- Construction end7 weeks lateforecast Sep 17, 2017