Valley Regional Hospital Laundry Upgrade

Kings, Nova Scotia

completeHealthcare InfrastructureCVRIS
Federal contribution
$56,000
Federal share80%

of $70.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 27, 2021
Built

Approved 3 months before the announcement.

Program
COVID-19 Resilience Stream
Ultimate recipient
Province of Nova Scotia
Construction start
Jun 1, 2021(actual)
Construction end
Dec 13, 2021(actual)

Against the original forecast

  • Construction end3 weeks lateforecast Nov 19, 2021