Upgrade of the fire alarm system by adding general call functionality
Federal contribution
$50,231
Federal share80%
of $62.8K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 7, 2021
20222023
Built
Approved 4 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Centre intégré universitaire de santé et de services sociaux de la Capitale-Nationale
- Construction start
- Jan 1, 2023(actual)
- Construction end
- Jun 1, 2023(actual)
Against the original forecast
- Construction start6 months lateforecast Jul 1, 2022
- Construction end5 weeks lateforecast Apr 30, 2023