Back to projects

Renewal of water pipes

Beaupré, Quebec

completeDrinking WaterCWWF
Federal contribution
$2.5M
$2,498,900
Federal share49%

of $5.1M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 1, 2017
20172018
Built

Approved 6 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
City of Beaupré
Construction start
Jun 5, 2017(actual)
Construction end
Aug 31, 2018(actual)

Against the original forecast

  • Construction start5 weeks lateforecast May 1, 2017
  • Construction end7 months earlyforecast Mar 31, 2019

Also in Beaupré