Replacement of the L-00211 server room air conditioning system and replacement of end-of-life decentralized UPS (emergency battery) for a centralized UPS
Federal contribution
$1.1M
$1,087,571
Federal share80%
of $1.4M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 7, 2021
202220232024
Built
Approved 4 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Centre intégré universitaire de santé et de services sociaux de la Capitale-Nationale
- Construction start
- Aug 1, 2022(actual)
- Construction end
- Dec 31, 2023(actual)