Reconfigure and renovate some office spaces in the finance and human resources department

Montréal, Quebec

completeEducation, Training and ChildcareCVRIS
Federal contribution
$658,252
Federal share80%

of $825.4K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 8, 2021
Built

Approved 4 months before the announcement.

Program
COVID-19 Resilience Stream
Construction start
Mar 5, 2021(actual)
Construction end
Sep 30, 2021(actual)

Against the original forecast

  • Construction end4 weeks earlyforecast Oct 31, 2021

Also in Montréal