Schedule

Announced and approvedJul 7, 2021
202220232024
Built

Approved 4 months before the announcement.

Program
COVID-19 Resilience Stream
Construction start
Apr 1, 2022(actual)
Construction end
Dec 31, 2023(actual)

Against the original forecast

  • Construction start9 months lateforecast Jul 1, 2021