Renovations to the changing rooms in Pavilion D

Montréal, Quebec

completeEducation, Training and ChildcareCVRIS
Federal contribution
$696,350
Federal share69%

of $1.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 8, 2021
202220232024
Built

Approved 4 months before the announcement.

Program
COVID-19 Resilience Stream
Ultimate recipient
Cégep Saint-Laurent
Construction start
May 31, 2023(actual)
Construction end
Mar 1, 2024(actual)

Against the original forecast

  • Construction end4 weeks earlyforecast Mar 31, 2024