Skylights Renovation on the roof of the Charlesbourg Campus
Federal contribution
$624,431
Federal share75%
of $835.4K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 8, 2021
Built
Approved 4 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Cégep de Limoilou
- Construction start
- May 31, 2021(actual)
- Construction end
- Oct 8, 2021(actual)
Against the original forecast
- Construction end6 weeks lateforecast Aug 27, 2021