Upgrading of the emergency power supply
Federal contribution
$2.0M
$2,000,000
Federal share80%
of $2.5M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 7, 2021
20222023
Built
Approved 4 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Centre intégré universitaire de santé et de services sociaux de la Mauricie-et-du-Centre-du-Québec.
- Construction start
- Jun 1, 2022(actual)
- Construction end
- Sep 28, 2023(actual)
Against the original forecast
- Construction end10 months lateforecast Dec 1, 2022
Also in Shawinigan
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 59075 in the federal list. How to read these figures.