A and 3X Walls Renovation
Federal contribution
$200,000
Federal share26%
of $770.1K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 8, 2021
Built
Approved 4 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Cégep de Limoilou
- Construction start
- Jun 1, 2021(actual)
- Construction end
- Nov 8, 2021(actual)
Against the original forecast
- Construction end6 weeks lateforecast Sep 24, 2021