Classrooms Renovation at the Quebec and Charlesbourg campuses

Québec, Quebec

completeEducation, Training and ChildcareCVRIS
Federal contribution
$300,000
Federal share76%

of $397.3K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 8, 2021
Built

Approved 4 months before the announcement.

Program
COVID-19 Resilience Stream
Ultimate recipient
Cégep de Limoilou
Construction start
May 27, 2021(actual)
Construction end
Aug 13, 2021(actual)

Against the original forecast

  • Construction end4 weeks lateforecast Jul 16, 2021

Also in Québec

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 59079 in the federal list. How to read these figures.