Back to projects

Fire Pump Connection and Generator Replacement

Québec, Quebec

completeEducation, Training and ChildcareCVRIS
Federal contribution
$200,000
Federal share36%

of $548.4K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 8, 2021
2022
Built

Approved 4 months before the announcement.

Program
COVID-19 Resilience Stream
Ultimate recipient
Cégep de Limoilou
Construction start
Jun 28, 2021(actual)
Construction end
Jul 15, 2022(actual)

Also in Québec

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 59082 in the federal list. How to read these figures.