Back to projects

Non-gendered restrooms retrofit

Gatineau, Quebec

completeEducation, Training and ChildcareCVRIS
Federal contribution
$923,890
Federal share80%

of $1.2M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 8, 2021
2022
Built

Approved 4 months before the announcement.

Program
COVID-19 Resilience Stream
Ultimate recipient
Cégep de l'Outaouais
Construction start
Apr 12, 2021(actual)
Construction end
Dec 31, 2021(actual)

Also in Gatineau

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 59093 in the federal list. How to read these figures.