Replacement of generators at the Gabrielle-Roy and Félix-Leclerc Campuses

Gatineau, Quebec

completeEducation, Training and ChildcareCVRIS
Federal contribution
$271,525
Federal share80%

of $339.4K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 8, 2021
2022202320242025
Built

Approved 4 months before the announcement.

Program
COVID-19 Resilience Stream
Ultimate recipient
Cégep de l'Outaouais
Construction start
Nov 22, 2022(actual)
Construction end
Mar 31, 2025(actual)

Against the original forecast

  • Construction end3 months lateforecast Dec 31, 2024

Also in Gatineau

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 59094 in the federal list. How to read these figures.