Back to projects

Swimming Pool Renovation (Bleachers and Changing Rooms)

Shawinigan, Quebec

completeVentilationCVRIS
Federal contribution
$710,600
Federal share80%

of $888.3K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 8, 2021
20222023
Built

Approved 4 months before the announcement.

Program
COVID-19 Resilience Stream
Ultimate recipient
Cégep de Shawinigan
Construction start
May 3, 2021(actual)
Construction end
Dec 12, 2022(actual)

Also in Shawinigan

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 59097 in the federal list. How to read these figures.