Decks Renovation
Federal contribution
$226,926
Federal share74%
of $307.4K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 8, 2021
Built
Approved 4 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Cégep de Sherbrooke
- Construction start
- May 28, 2021(actual)
- Construction end
- Nov 18, 2021(actual)
Against the original forecast
- Construction end8 months earlyforecast Jul 15, 2022
Also in Sherbrooke
- South bypass of the Sherbrooke agglomeration by extending Highway 410 - Phase II$35.6M
- Expansion of Cabana Operations Center$30.8M
- Acquisition of 40 electric buses$24.8M
- Multipurpose Centre at Bishop's University - Sherbrooke$13.2M
- Renovation of Sherbrooke, Deauville and Brompton water treatment plants$6.5M
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 59100 in the federal list. How to read these figures.