Water Heaters Replacement in Building 1
Federal contribution
$162,073
Federal share80%
of $203.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 8, 2021
20222023
Built
Approved 4 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Cégep de Sherbrooke
- Construction start
- Feb 27, 2023(actual)
- Construction end
- Aug 10, 2023(actual)
Against the original forecast
- Construction end7 weeks earlyforecast Sep 30, 2023
Also in Sherbrooke
- South bypass of the Sherbrooke agglomeration by extending Highway 410 - Phase II$35.6M
- Expansion of Cabana Operations Center$30.8M
- Acquisition of 40 electric buses$24.8M
- Multipurpose Centre at Bishop's University - Sherbrooke$13.2M
- Renovation of Sherbrooke, Deauville and Brompton water treatment plants$6.5M
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 59101 in the federal list. How to read these figures.