Opening of a University Family Medicine Group (GMF-U) - Addition of a dedicated elevator

Montréal, Quebec

completeHealthcare InfrastructureCVRIS
Federal contribution
$500,000
Federal share80%

of $625.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 7, 2021
202220232024
Built

Approved 4 months before the announcement.

Program
COVID-19 Resilience Stream
Construction start
Apr 20, 2021(actual)
Construction end
May 30, 2024(actual)

Against the original forecast

  • Construction start7 weeks lateforecast Mar 1, 2021
  • Construction end19 months earlyforecast Dec 30, 2025

Also in Montréal

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 59104 in the federal list. How to read these figures.