Creation of an administrative wing and doctor's offices and rationalization of the medical library on the ground floor of the J.A. Desève pavilion
Federal contribution
$400,000
Federal share80%
of $500.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 7, 2021
2022
Built
Approved 4 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Centre intégré universitaire de santé et de services sociaux de l'Est-de-l'Île-de-Montréal
- Construction start
- Apr 12, 2021(actual)
- Construction end
- May 17, 2022(actual)
Against the original forecast
- Construction start6 weeks lateforecast Mar 1, 2021
- Construction end7 months earlyforecast Dec 24, 2022
Also in Montréal
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 59111 in the federal list. How to read these figures.