Demolition of the 3rd and 4th floors of the E wing of the Maisonneuve building
Federal contribution
$580,000
Federal share80%
of $725.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 7, 2021
2022
Built
Approved 4 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Centre intégré universitaire de santé et de services sociaux de l'Est-de-l'Île-de-Montréal
- Construction start
- Jan 15, 2022(actual)
- Construction end
- May 17, 2022(actual)
Against the original forecast
- Construction start2 months lateforecast Nov 8, 2021
- Construction end19 months earlyforecast Dec 31, 2023
Also in Montréal
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 59112 in the federal list. How to read these figures.