Asbestos removal from the technical vacuum under the endoscopy unit in anticipation of its upgrading

Montréal, Quebec

completeHealthcare InfrastructureCVRIS
Federal contribution
$1.2M
$1,200,000
Federal share80%

of $1.5M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 7, 2021
202220232024
Built

Approved 4 months before the announcement.

Program
COVID-19 Resilience Stream
Construction start
Mar 31, 2021(actual)
Construction end
May 30, 2024(actual)

Against the original forecast

  • Construction start4 weeks lateforecast Mar 1, 2021
  • Construction end2 months earlyforecast Jul 31, 2024