Asbestos removal from the technical vacuum under the endoscopy unit in anticipation of its upgrading
Federal contribution
$1.2M
$1,200,000
Federal share80%
of $1.5M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 7, 2021
202220232024
Built
Approved 4 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Centre intégré universitaire de santé et de services sociaux de l'Est-de-l'Île-de-Montréal
- Construction start
- Mar 31, 2021(actual)
- Construction end
- May 30, 2024(actual)
Against the original forecast
- Construction start4 weeks lateforecast Mar 1, 2021
- Construction end2 months earlyforecast Jul 31, 2024