G Wing windows replacement
Salaberry-de-Valleyfield, Quebec
Federal contribution
$970,900
Federal share62%
of $1.6M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 8, 2021
2022
Built
Approved 4 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Cégep de Valleyfield
- Construction start
- Dec 6, 2021(actual)
- Construction end
- Nov 17, 2022(actual)
Against the original forecast
- Construction end4 weeks earlyforecast Dec 14, 2022