Replacement of various roof ponds coverings
Federal contribution
$750,000
Federal share61%
of $1.2M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 8, 2021
20222023
Built
Approved 4 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Cégep du Vieux-Montréal
- Construction start
- May 29, 2023(actual)
- Construction end
- Nov 8, 2023(actual)