Major retrofit of the Sports Center locker rooms

Montréal, Quebec

completeEducation, Training and ChildcareCVRIS
Federal contribution
$550,500
Federal share41%

of $1.4M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 8, 2021
2022
Built

Approved 4 months before the announcement.

Program
COVID-19 Resilience Stream
Ultimate recipient
Cégep du Vieux-Montréal
Construction start
Jun 21, 2021(actual)
Construction end
Feb 2, 2022(actual)

Against the original forecast

  • Construction end8 weeks lateforecast Dec 6, 2021

Also in Montréal

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 59126 in the federal list. How to read these figures.