Repair and compliance of exterior facades
Federal contribution
$132,219
Federal share49%
of $267.7K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 8, 2021
2022
Built
Approved 4 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Collège LaSalle
- Construction start
- Jul 30, 2021(actual)
- Construction end
- Nov 15, 2022(actual)
Against the original forecast
- Construction end7 weeks lateforecast Sep 30, 2022
Also in Montréal
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 59131 in the federal list. How to read these figures.