Upgrade to reinforce pavilion C floor
Federal contribution
$783,180
Federal share80%
of $979.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 7, 2021
2022
Built
Approved 4 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Centre intégré de santé et de services sociaux de la Montérégie-Centre
- Construction start
- Sep 27, 2021(actual)
- Construction end
- Oct 16, 2022(actual)
Against the original forecast
- Construction start3 months lateforecast Jun 21, 2021
- Construction end5 months lateforecast Jun 1, 2022
Also in Longueuil
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 59134 in the federal list. How to read these figures.